When mrp ii systems include feedback to revise a plan that is not feasible, they are known as?

Respuesta :

LearnGrow
LearnGrow LearnGrow
  • 31-05-2018
MRP stands for Manufacturing Resource Planning.
When MRP II systems include feedback to revise a plan that is not feasible, they are known as closed loop MRP. The closed loop MRP includes products that have been returned by retail stores, or products that did not meet the manufacturer's quality control standards. 
It is used for production planning and inventory control.
Answer Link

Otras preguntas

What is a Punnett Square? How can it be used to analyze possible genetic outcomes for offspring?
The National Reclamation Act directly affected the management of which natural resource? A. oil B. coal C. water D. lumber
If 1+4=5 2+5=12 3+6=21 8+11=
Robert is using the following data samples to make a claim about the house values in his neighborhood: House Value A $250,000 B $275,000 C $300,000 D $267,000
A fraction that is equivalent to 3/6
What country is noted for beginning the Renaissance movement? A. England B. France C. Germany D. Italy
What is pre-atrial contraction and how do you treat it
Two factors that contribute to a detrimental relationship
Read the passage: From forth the fatal loins of these two foes A pair of star-cross'd lovers take their life; Whose misadventured piteous overthrows Do with the
6,5000cL=how many leters