The critical path on a project can change as the project progresses. select one:

a. true

b. false

Respuesta :

mirrorkitten
mirrorkitten mirrorkitten
  • 02-04-2019

The answer is True.

In project management, critical path refers to a sequence of stages that would require the smallest amount of time possible to bring a project to completion.

Critical path can change during a project since there might be circumstances during it which would lead certain activities to be finished longer or faster. Critical path can be determined by a specialized algorithm technique.

Answer Link

Otras preguntas

what is the longest word in the english dictionary
What diseases do air pollutants cause?
A rectangular box is 5 in. ​wide, 5 in. ​tall, and 4 in. long. What is the diameter of the smallest circular opening through which the box will​ fit?
What are legends? Most fictional stories about events that happened in the past.
Fraction equivalent to 7/2
what was the peral harbor ​
Which sentence has a vague pronoun error? A) Some of these poems are more difficult than others depending on the poet. B) The English teacher explained similes
Compare and contrast the functions of carbohydrates to the function of proteins
what is the rate of $120 for 15 books written as a unit rate? thank u
How are tribal governments most like the U.S. government? A. Each has no responsibility to the states. B. Each has officials who manage religious ceremonies. C.