seven people need 90 days to repair and paint a heritage building.if the job should be completed in 15 days.how many more people need to be employed.​

Respuesta :

khababnazir10
khababnazir10 khababnazir10
  • 22-11-2019

Answer:

Here is your answer mate

Step-by-step explanation:

As we know that 7 person take 90 days so 1 person takes 90×7=630 days

As work has to be finished in 15 days than 630/15=42 so

42 people can complete work in 15 days but as we have already 7 people employed so required are

42-7=35 so 35 more are needed

Answer Link

Otras preguntas

if 9^x-9^x-1=24, then find the value of (6x)^x
A rocket lifted off from a launch pad and traveled vertically 30 km, then traveled 40 km at 30 degrees from the vertical, and then traveled 100 km at 45 degrees
container is 5 meters wide ,6meters long and 3 meters in depth what is the capacity in quarts
How is 'hearing' a motif in the novel A Separate Peace by John Knowles?
A rocket lifted off from a launch pad and traveled vertically 30 km, then traveled 40 km at 30 degrees from the vertical, and then traveled 100 km at 45 degrees
solve using the substitution and elimination method 3a-12b=9 4a-5b=3 can someone please help?
The scale of a square map indicates that each inch on the map corresponds to 5 miles. Write an expression that describes the area of land shown on the map. If t
Why are the irish famous for drinking?
How is 'hearing' a motif in the novel A Separate Peace by John Knowles?
How is 'hearing' a motif in the novel A Separate Peace by John Knowles?