The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

Common ratio of -1,1,4,8,…
what is the exact length of the missing side​
Wind is • air moving from areas of high pressure to areas of low pressure. • air moving from areas of low pressure to areas of high pressure. air moving from ar
What is the Keeling Curve and Why is it so Famous?
What is a transaction that has not been processed yet by a financial institution?
Can you help finish my trigonometry maze?? And show me the equation for each I know some of them are finding angles and I’m stuck please help.
During the beginning of the American Industrial Revolution, government usually did which of the following? A. Favored big business B. Ignored big business C. St
Animals, mushrooms and molds are all examples of what? A. Autotrophs B. Heterotrophs C. Fungi D. Plants I will give brainliest
A swimmer swims the 400 meter freestyle in 5 minutes, What is his speed? A. 80 m/min B. 0.01 m/min C. 2000 m/min
Expressions equivalent to 16x+12