a field can be cleared by 33 men in 15days. how many more person required if the field has to be cleared 4 days earlier?​

Respuesta :

wsookhuei
wsookhuei wsookhuei
  • 24-10-2020

Answer:

12 men

Step-by-step explanation:

33men x 15 days = the whole project

Let the men that are required be x.

33 x 15 = (15-4)x

495 = 11x

x = 45

Answer Link

Otras preguntas

¿Que es una fuente luminosa?
It is commonly said that humans have 206 bones, but this is not always true. Explain using the term "sutural bones."​
Pls help: What is the net equation for CNO cycle?
Body image can affect a person's health. Please select the best answer from the choices provided. T F Please select the best answer from the choices provided. A
Find a slope of a line that passes through (2,4) and (1,7)
HURRY PLEASE!! I’ll mark you as brainliest!! im being timed the graph represents the water path of a fire hose. what is the maximum value of the function? expla
Read the excerpt from a speech by US Secretary of Education Arne Duncan. What is the speech’s purpose? A. to inform the country what students are learning in t
What do you think this quote is trying to say? (comment on the following quote ) “I looked at the three of them standing there and I felt that I was seeing the
Which is one factor of rock types that affects the rate of weathering? porosity moisture temperature mineral color
Consider the function f(x) = x^3 - 7x^2 - 2x + 14 What is the total number of zeros of f(x)? Explain how you got your answer. Find the zeros of f(x). Explain yo