If 3 men can paint 4 houses in 5 days , how many days does it take for 7 men paint 14 houses ??? help me plz

Respuesta :

bestbabe
bestbabe bestbabe
  • 22-05-2021

Answer:

3men = 4houses= 5days

7men= 14houses= x days

14÷7 = 2days

Answer Link

Otras preguntas

Connor White is the grandson of one of the country's wealthiest businessmen. The White family has been wealthy for generations, and Connor stands to inherit the
Find the simple interest on $5,000 at 4% interest for 3 years.
Huilan's age is two times Thomas's age. The sum of their ages is 27. What is Thomas's age?
Supposed the income elasticity of demand for renting apartments i. Rhode island is estimated at -1.25. Based o. This estimate, are renting apartments in Rhode I
why did the nineteenth amendment passed during the progressive era but not before
Why is a certificate of deposit considered such a safe investment? It is guaranteed by the federal government. It is issued by a savings bank. It p
Is it fair for some people in society to have more power than others? Is it fair for those who disobey to be punished greatly? In the context of this text, what
Analyze the diagram below and complete the instructions that follow. Find . A. B. C. D.
A meter stick is place in a very high-speed spaceship. What length would the astronauts say the meter stick was? What would the length of the meter stick be as
Tony charges a capacitor and then discharges it through a resistor. He notices that, after two time constants, the voltage across the capacitor has decreased to