When building a house, the number of days required to build is inversely
proportional to with the number of workers. One house was built in 57 days by 6
workers. How many days would it take to build a similar house with 19 workers?

Respuesta :

latrelhunter49
latrelhunter49 latrelhunter49
  • 27-05-2021

Answer:

It would take 38 days for them to build a similar house

Answer Link

Otras preguntas

An example of a stateless nation in the middle east is provided by who?
Which is the correct sequence of events during embryonic development? (A) cleavage — differentiation — fertilization — gastrulation (B) differentiation — fertil
What is a common multiple of 3,4,5 and 6?
Write an equation in slope intercept form of a line that passes through the point (2,4) and is perpendicular to the graph of x-6y=2
Why do grapes grow well in the Finger Lakes region?
If the tax rate is 6.5%, what is the tax on $80?
Suppose Maya made another sign with an area of 48 square inches. Would this sign be larger or smaller than the sign with an area of 48 square centimeters? Expla
how to separate salt and sugar?
which type of livestock were raised in mission san francisco de asis
Solve by Elimination.x + 2y = 73x - 2y = -3