When building a house, the number of days required to build varies inversely with
with the number of workers. One house was built in 21 days by 17 workers. How
many days would it take to build a similar house with 7 workers?

Respuesta :

angelxziplier
angelxziplier angelxziplier
  • 26-05-2021

Answer:

51 days

Step-by-step explanation:

17/7= 2.428

2.428*21=50.988=51

Answer Link

Otras preguntas

One central belief of Christianity is that Responses A. three different gods make up the trinity. B. true believers must become martyrs. C. forgiveness is unatt
25 POINTS PLEASE HELP ME!!! IM SO CLOSE TO FAILING RN ITS NOT FUNNY
solve for 5^2+2(4)+8+4
How did Fredrick Henry's view of war change in farewell to arms
Complete the real-world situation that could be modeled by the equation 140 - 8x = 180 - 12x . Xavier has $140 in his lunch account . He spends $ in his lunch a
A force of 9 N acts on an object for 0.63 seconds.
All of the following are found in a DNA molecule except
Where does carriage comes in Financial statements?
Television had a major impact on pop music in America. How is this BEST demonstrated? OA. Frank Sinatra and Bing Crosby created a unique way of conversing with
Which number is equal to 63?