The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.
a. late start date
b. early finish date
c. late finish date
d. early start date

Respuesta :

azaleambailey
azaleambailey azaleambailey
  • 24-02-2018
A. Late start date because the other ones done work
Answer Link

Otras preguntas

The scientific term for a living thing is
Circle 6 numbers for a total of 31.8,9,91,5,81,1,1
is 5/12 bigger than 3/7
What features distinguish anthropoids from strepsirrhines
Jessica was solving an equation. After she finished simplifying, her result was 0=2. This result confused her. Explain to Jessica what her result means. Explain
Jessica was solving an equation. After she finished simplifying, her result was 0=2. This result confused her. Explain to Jessica what her result means. Explain
Leo has a total of 45c. he has some dimes and pennies . How many  different combinations of dimes and pennies could Leo have?make a table to solve.
Is 0.602 equvalent to 0.62
Leo has a total of 45c. he has some dimes and pennies . How many  different combinations of dimes and pennies could Leo have?make a table to solve.
Why do the track runners start at different positions on the track?