If A completes a particular work in 8 days and B the same work in 24 days. How many days will it take if they work together?

Respuesta :

Аноним Аноним
  • 25-02-2018
A:
1 day = 1/8 of work

B:
1 day = 1/24 of the work

Together:
 1 day = A + B = 1/8 + 1/24 = 4/24 = 1/6

1 day = 1/6 of work
1/6 x 6 of work = 1 x 6 days
work =  6 days 

Answer Link

Otras preguntas

Make a list of problems and your suggestions in development of transport in your district​
……Is an area of reddening of a person's skin, sometimes with raised spots, appearing specially as a result of allergy or illness.
Which statement about workplaces is true ? a ) Many companies commit to diversity in their corporate mission statements . b) People in one company generally t
5 (atleast 2) contributions of Mamata Banerjee?​
How do we analyse the use of diction and imagery and other features of language in the poem Repair by finuala dowling ​
methemetikcs but anyways yea I don't understand this I'm any way shape or form.​
How much work does a supermarket checkout attendant do on a can of soup he pushes 0.420 m horizontally with a force of 4.60 N? Express your answer in joules and
Complete each sentence with one of these verbs : answer, apply, lie, make, try, walk, wash, write, wait, wear.
History I need help !
Which pair shows equivalent expressions? O 2x+10=-2(x-5) O-2(x+5)=2x-10 0 -2x-10=-2(x+5) O -2(x-5)=-2x-10